Project wise achievements

Sewage Treatement Plant - 250 KLD STP, Nila & Gayathri (Technopark Phase-I)
  • Project Start Date

    2023-08-05

  • Project Cost

    235.0 lakhs

  • Category

    Construction

  • Project End Date

    2024-05-15

  • Physical Progress

    50.0 %

  • .

Sewage Treatement Plant -750 KLD (Civil & MEP Works)-Technopark Phase-III
  • Project Start Date

    2022-08-01

  • Project Cost

    473.0 lakhs

  • Category

    Construction

  • Project End Date

    2023-06-01

  • Physical Progress

    100.0 %

  • .

Solid Waste Management Plant (Technopark Phase-III)
  • Project Start Date

    2024-01-19

  • Project Cost

    42.0 lakhs

  • Category

    Construction

  • Project End Date

    2024-06-23

  • Physical Progress

    66.67 %

  • .

Compound Wall/Rain Water Harvesting Ponds (Technopark Phase-III)
  • Project Start Date

    2022-06-14

  • Project Cost

    361.0 lakhs

  • Category

    Construction

  • Project End Date

    2023-03-14

  • Physical Progress

    99.0 %

  • .

Culverts/ Internal Road (Technopark Phase-III)
  • Project Start Date

    2023-01-04

  • Project Cost

    116.0 lakhs

  • Category

    Construction

  • Project End Date

    2023-07-04

  • Physical Progress

    100.0 %

  • .

Grid Connected Rooftop solar power plant (25kwp and 78kwp at Park Centre Building and Pump House Water Tank)- Technopark Phase-I Campus..
  • Project Start Date

    2023-12-02

  • Project Cost

    64.0 lakhs

  • Category

    Construction

  • Project End Date

    2024-05-07

  • Physical Progress

    22.22 %

  • .

QUAD - IT Building by TECHNOPARK (Technopark Phase-IV)
  • Project Start Date

    2023-07-01

  • Project Cost

    38100.0 lakhs

  • Category

    Construction

  • Project End Date

    2027-12-31

  • Physical Progress

    11.5 %

  • .

Construction of Compound Wall (Technopark Phase IV Campus)
  • Project Start Date

    2023-02-10

  • Project Cost

    130.0 lakhs

  • Category

    Construction

  • Project End Date

    2023-09-10

  • Physical Progress

    98.0 %

  • .

Construction of Commercial Building (Technopark Phase-1 Campus)
  • Project Start Date

    2023-02-01

  • Project Cost

    3000.0 lakhs

  • Category

    Construction

  • Project End Date

    2024-04-01

  • Physical Progress

    33.86 %

  • .

Construction of Compound Wall (Technopark Phase I Campus)
  • Project Start Date

    2023-09-15

  • Project Cost

    215.0 lakhs

  • Category

    Construction

  • Project End Date

    2024-03-20

  • Physical Progress

    80.0 %

  • .

1 MLD Fully Automated Water Treatment Plant with Nano-Filtration Technology (Technopark Phase I Campus)
  • Project Start Date

    2023-09-18

  • Project Cost

    258.0 lakhs

  • Category

    Construction

  • Project End Date

    2024-10-20

  • Physical Progress

    62.86 %

  • .

EAM with Computerized Maintenance Management System.
  • Project Start Date

    2023-11-18

  • Project Cost

    50.0 lakhs

  • Category

    Digital Infrastructure

  • Project End Date

    2024-07-18

  • Physical Progress

    97.5 %

  • .

Automated Chiller Plant with Tenant Billing Services (Technopark Phase I Campus - Bhavani Building)
  • Project Start Date

    2023-11-11

  • Project Cost

    490.0 lakhs

  • Category

    Construction

  • Project End Date

    2024-10-11

  • Physical Progress

    42.86 %

  • .